The Jann-Berghaus Bridge in Leer
The Jann-Berghaus Bridge in Leer Second Bridge
Between 1948 and 1950 a new bridge was built. At its opening it was the largest swing bridge in the world.[3] It was demolished in 1991 due to structural defects. It bore the name Jann-Berghaus Bridge after Jann Berghaus (1870–1954), who among other things was president of the East Frisian Landscape and was very committed to regional concerns.

Third Bridge Construction
From 1989 to 1991 a new Jann-Berghaus Bridge was built in the form of a bascule bridge with a clearance width of 40 meters. On May 17, 1991, the new bridge was put into service after two years of construction. The construction costs amounted to 40.1 million DM.[6]

Widening of the clearance
New buildings of the Meyer Werft in Papenburg are transferred to the North Sea several times a year on the Ems. The Jann-Berghaus Bridge represents a navigation obstacle on the way to the North Sea, therefore Meyer Werft pushed for a widening of the clearance opening. The construction work began in summer 2008 and was completed in spring 2010.

Even before the necessary permits were granted, soil investigations were carried out at the bridge from September 2007. From November 2007, after the Water and Shipping Directorate Aurich had approved the conversion, evidence preservation was carried out on the houses in Leerort.

In June 2008 there was damage to the bottom of the construction pit, a damage point had formed when pumping out the sheet pile box. To prevent the damage from spreading, the construction pit was flooded again on June 17.

On July 28, 2008, the bridge was closed to traffic. As a replacement, a ferry connection between Bingum and Leerort with the ferry Julius was set up for pedestrians, cyclists and drivers of small motorcycles[17], while larger vehicles had to take a detour.[19] The contract for the ferry operation was awarded to Briese Shipping from Leer.[20] Roads were rebuilt in the Leer city area to handle the expected higher traffic volume due to the bridge closure as smoothly as possible. The new lanes are to be permanently retained to permanently improve the traffic situation.[21]

Initially, a part of the fixed reinforced concrete bridge with a length of 38 meters was cut and removed with the help of a floating crane. On the east side of the existing bridge leaf (bascule) a current pier was blown up on August 16, 2008 with a controlled explosion with 400 kilograms of explosives, then removed with excavator equipment and rebuilt closer to the shore. An additional, but smaller bridge leaf was then installed on it.

The new components were produced in Poland and arrived in Leer from November 2008.[28]

Originally the bridge was to be reopened to traffic about four months later at the end of November 2008, but this date was initially delayed until May 2009. Finally, the bridge was reopened to traffic on August 29, 2009.[35] Subsequently, there were still occasional shorter closures.[36][37] The work was accepted in March 2010.[38]

The conversion increased the clearance width to about 56 meters. The conversion cost 17.7 million euros.' role="button">